Taekwon V Land is finally opening!!!

Machine translated



It was originally scheduled to open in December, but it will have a soft opening this month to coincide with the Firefly Festival.
The budget, which was initially 7.2 billion KRW, has already ballooned to 21.7 billion KRW.
This is a project being undertaken in Muju County, which has a population of only 23,412.
The project structure has suddenly shifted from a joint-venture corporation model to a private outsourcing model just before the opening.
If deficits occur, the county is expected to cover the entire amount.