The breakdown of the construction contract between KHNP and Daewoo E&C for the Czech nuclear power plant is ultimately due to unreasonable low-ball bidding

Machine translated

‌





This project has been delayed for over a year due to process design that overlooked the strict local licensing procedures and design approval methods in Europe.
This setback occurred because they insisted on the Korean method of starting construction first, rather than the European procedure of commencing construction only after the design is finalized and approved.
Such large-scale losses by KHNP have directly led to the deterioration of the performance of its parent company, KEPCO, through consolidated financial statements. For KEPCO, which is already struggling with over 200 trillion won in debt, the poor performance of its subsidiary's overseas business has become an unexpected variable hindering the improvement of its financial structure. This can lead to an increase in the cost of power supply, ultimately acting as a factor that intensifies pressure to raise electricity rates.
While it was an ambitious challenge to pioneer new overseas markets, it is difficult to avoid criticism that the forced implementation of the project without thorough risk assessment has placed a burden on the livelihood of the people.
However, KEPCO and KHNP are currently in litigation regarding the 1.4 trillion won construction cost of the Barakah nuclear power plant. The Barakah nuclear power plant is a project worth approximately 22.6 trillion won, which was the first overseas nuclear power plant contract secured by Korea in 2009. KEPCO is the main contractor, and KHNP was responsible for tasks such as operations during the construction process. The Barakah nuclear power plant, consisting of four units, began commercial operation sequentially from Unit 1 in 2021 to Unit 4 in September 2024.
However, disputes began as construction costs swelled beyond expectations due to delays in the construction period and rising labor costs. KHNP argued that the main contractor, KEPCO, should pay an additional 1 billion USD (approximately 1.4 trillion won) in construction costs, while KEPCO countered that they could only pay after receiving settlement from the UAE side first.
Korea's current nuclear power exports are not a jackpot, but an empty shell.
KEPCO and KHNP are already in a dispute over increased construction costs at the Barakah plant, and the Czech nuclear plant was also secured through low-ball bidding.
Since nothing is left after being stripped of IP fees and other costs by Westinghouse, negotiations between KHNP and Daewoo E&C regarding construction costs have broken down.